Haware My First Home, Shil Phata: Environment Clearance for a greenfield township build

large residential construction site in an Indian city with towers rising and gre

01 02

Location
Village Shil, District Thane, Maharashtra
Market
Real Estate & Construction
Client
Haware Properties LLP
Practice
Environmental Approvals

A greenfield residential and commercial development at Shil Phata in Thane, in a residential-plus-commercial zone under Thane Municipal Corporation. Above the built-up threshold, which is what brings a housing project inside the EIA Notification and makes the clearance a gate rather than a formality.

The brief

Haware Properties proposed a residential and commercial building at Shil Phata, on survey numbers 83/1, 84/2, 85/1A and 85/2A in Village Shil, Thane. The development plan places the site in a residential-plus-commercial zone, and the project is greenfield, under the jurisdiction of Thane Municipal Corporation.

At 98,746.54 sq m of total construction the project sits well above the threshold at which the EIA Notification applies to building and construction, so an Environment Clearance had to be secured before ground was broken rather than alongside the build.

98,746.54 m²

Total construction area

The mandate

Area statement
Plot, net plot, FSI, non-FSI and total construction established as the figures the whole application is appraised against.
Category screening
The project placed against the schedule to the EIA Notification for item 8 building and construction, which decides the route it takes.
Application and documentation
Form-1 and Form-1A with the supporting environmental documentation a built-environment proposal requires.
Appraisal
The file carried through appraisal to grant, with the conditions it would operate under set out for the client.

The area statement

A building-and-construction clearance turns on area. These are the figures the application was made on.

Total plot area
16,280.00 sq m.
Net plot area
14,118.89 sq m.
Proposed FSI area
76,314.69 sq m.
Non-FSI area
22,431.85 sq m.
Total construction area
98,746.54 sq m.

The outcome

The clearance was applied for on a fully stated area position, which is the part of a building application most often argued over: a plot and a net plot that do not reconcile, or an FSI figure that moves between the plan and the form, is how a file acquires months. Here the numbers were fixed once and carried through.

98,746.54 m²
Construction area cleared for
TMC
Jurisdiction the project sits under
Greenfield
Site condition at application

Planning a project like this one?

Tell us about your site and your timeline. We will set out the approvals, the plan and the team to deliver it.